October 2026

Underground plumbing work for Buildings 1, 2, 3, 4, 9, 10 and the amenity clubhouse is complete. Allowing footings to be poured, foundation masonry walls to be set, termite treatment to be implemented, with slabs now being poured…

Read More
Hart RobertsElm Hill
September 2026

For the remainder of September work will be focused on getting building slabs poured with the vertical masonry work being completed on these early buildings to allow framing to commence in October…

Read More
Hart RobertsElm Hill
August 2026

The offsite work within Morehead Ave is now complete, along with the underground plumbing work for Buildings 1, 2, 3, 4. The foundation footings have been poured for Buildings 3 and 4, with masonry walls starting. The roadways are taking shape with the two main roadways that run perpendicular to Morehead Ave…

Read More
Hart RobertsElm Hill