November 2026
Framing is now rapidly advancing at Elm Hill. Building 3 is fully framed with its roof trusses set, and roofing underway. Building 4 is close behind, with roof trusses being set earlier this week. Framing on Building 1 started at the start of this week, and Building 2 will be following right behind it.
The slabs for Buildings 5, 9, and 10 are being poured this week and into the start of next week, which keeps the next round of buildings ready for framing crews to keep moving. Windows are scheduled to arrive later this month and we expect Buildings 3 and 4 to be fully dried-in by the end of November, and Building 1 in early December, to allow interior work to progress.